PROJECT DETAILS
- Client: City of Woodlake
- Location: Woodlake, CA
- Year Completed: 2014
- Value: $1,644,217
- Project Type: Transportation
PROJECT DESCRIPTION
The Downtown Woodlake Enhancement project was constructed to beautify downtown Woodlake while provided much need ADA upgrades, storm drainage improvements, and landscaping. Avison construction phases 2 and 3 which encompassed a major portion of downtown Woodlake. A large portion of the project was located within Caltrans’ right of way and required significant cooperation among all parties involved.
SCOPE OF WORK
- Demolition of existing facilities
- 21,400 sf of patterned, colored concrete walks
- 11,650 sf of brick walks and crosswalks
- New curb & gutter and other misc. concrete improvements
- Minor AC Paving
- New storm drains
- Landscape and irrigation
- Benches, trash cans, bike racks, and lighted bollards
- New street lighting
- Striping and decorative signage